How to Accurately Analyze Progress, Budget, and Time on Tasks with GanttPRO: Graphical Reports

Written by: Andrew Stepanov

Andrew Stepanov

Content marketing lead, senior editor

Andrew is a seasoned marketing professional with over 10 years of experience as a writer and editor. Since 2017, he has been a content lead and content marketing strategist for GanttPRO.

See full bio
Reviewed by: GanttPRO Team

GanttPRO Team

Product development

Best practices in project management, productivity, and software solutions. Inspired by the experience of every GanttPRO team member.

See full bio

June 17, 2025 / Estimated reading time: 4 minutes

GanttPRO release: graphical reports

This release includes an updated Reports section with the new graphical ways of visualization.

With them, you’ll be able to more flexibly and accurately track and analyze your progress, budget, and time spent on tasks in one as well as multiple projects and even portfolios – graphically, all in one place.

Let’s get right into it.

What reports are available

First, let’s figure out why you may need these graphical reports in GanttPRO online Gantt chart software.

They will help you:

  • Better understand what is going on in your projects.
  • Identify deviations and possible risks faster.
  • Establish clear and transparent communication and collaboration with third parties such as stakeholders, clients, etc.

You’ll find all reports in the same Reports section in the left sidebar.

GanttPRO release: graphical reports

In addition to the two types, Time log and Budget analysis, that were previously available we’ve added 9 more.

All of these reports fall into 3 general categories:

  • Progress.
  • Budget.
  • Time on tasks.

To create one, simply select the type you want and click Create. A pop-up window will appear where you can select the options you want to include in your report.

GanttPRO release: graphical reports

Now, let’s go through each new report.

Progress reports

Here, you will find 5 new reports:

  • Milestone timeline.
  • Projects by status.
  • Project list.
  • Schedule variance.
  • Progress S-Curve.

Milestone timeline

This report will give you visual representation of your project’s milestones along a timeline that shows events by month.

You can include here one or several projects as well as portfolios.

GanttPRO release: graphical reports

Projects by status

This report will give you a color-coded pie chart overview of your projects based on their current statuses — on track, off track, at risk or under custom statuses.

You can include here one or several projects as well as portfolios.

GanttPRO release: graphical reports

Project list

This report will give you an overview of your projects. It will include a detailed table with key information such as a project name, its status, progress, owner, start and end dates.

You can include here one or several projects as well as portfolios.

GanttPRO release: graphical reports

Schedule variance

With the help of this report, you will understand whether project schedules are on track or running ahead/behind.

You can include here one or several projects as well as portfolios. Also, you can select a calculation mode: for multiple projects – Actual to planned; for one project – Actual to baseline or Planned to baseline.

If you see a negative value, it means that your project is behind schedule.

If you see a positive value, rest assured that your project is ahead of schedule.

Please note that all progress values are taken as of the current date.

GanttPRO release: graphical reports

Progress S-Curve

This report will help you track project cumulative actual and planned progress. In other words, you will see whether your project is on track or not.

You can include here just one project. Also, you can select a calculation mode: Actual to planned, Actual to baseline, or Planned to baseline.

GanttPRO release: graphical reports

Budget reports

Here, you will find 2 new reports:

  • Budget analysis by project.
  • Budget S-Curve.

The Budget analysis report remains the same.

Budget analysis by project

With the help of this report, you will be able to track cost variance by each project to ensure that you stay on budget and avoid overspending.

Note: the table version of this report is in development.

You can include here one or several projects as well as portfolios. In addition, you can select a calculation mode depending on how many projects you have: for multiple projects – Actual to planned; for one project – Actual to baseline or Planned to baseline.

GanttPRO release: graphical reports

Budget S-Curve

With this report, you’ll be able to track your project’s cumulative budget and actual cost. In other words, it shows your planned budget, real spendings, and the deviation from the planned budget.

It combines two types of visualization:

  • S-Curves. They show cumulative values for each month.
  • Bars. They show point values for each month.

Only one project is available for inclusion here. Also, you can select a calculation mode: Actual to planned, Actual to baseline, or Planned to baseline.

GanttPRO release: graphical reports

Time on tasks reports

Here, you will find 2 new reports:

  • Time on tasks analysis by project.
  • Time on tasks S-Curve.

The Time log report remains the same.

Time on tasks analysis by project

This report will help you track variance in working hours by each project. In other words, it shows the planned and spent time on tasks, as well as the variance between these values.

Note: the table version of this report is in development.

One and several projects as well as portfolios are available for inclusion here. Also, you can select a calculation mode depending on how many projects you have: for multiple projects – Actual to planned; for one project – Actual to baseline or Planned to baseline.

GanttPRO release: graphical reports

Time on task S-Curve

With this report, you’ll be able to track project cumulative time logged and estimated hours.

It combines two types of visualization:

  • S-Curves. They show cumulative values.
  • Bars. They show values for each month.

You can include here just one project. Also, you can select a calculation mode: Actual to planned, Actual to baseline, or Planned to baseline.

GanttPRO release: graphical reports

Need help?

If you have questions about how to work with new reports, ask us in the Live chat.

5 2 votes
Article Rating
Andrew Stepanov

Andrew Stepanov

Andrew is a seasoned marketing professional with over 10 years of experience as a writer and editor. Since 2017, he has been a content lead and content marketing strategist for GanttPRO.

GanttPRO Team

GanttPRO Team

Best practices in project management, productivity, and software solutions. Inspired by the experience of every GanttPRO team member.

Read also

From an Idea to a Plan in Minutes: Meet the AI Gantt Chart Maker
Andrew Stepanov/Estimated reading time: 3 minutes
How to Accurately Analyze Budget, Progress, and Time on Tasks with GanttPRO: Table Reports
Andrew Stepanov/Estimated reading time: 4 minutes
How to Delete Team Members from an Account and Keep Their Data: User Conversion
Andrew Stepanov/Estimated reading time: 1 minute
GanttPRO Wins Top Awards in Project Management and Other Related Fields
Paolo Kukhnavets/Estimated reading time: 5 minutes
How to Boost Productivity with GanttPRO: Filters for Google and Outlook Calendars Sync
Andrew Stepanov/Estimated reading time: 1 minute
How to Manage Projects with GanttPRO: Updated Board View
Andrew Stepanov/Estimated reading time: 4 minutes
GanttPRO Project Management Affiliate Program: Join It and Get the Highest Comission Rate
Paolo Kukhnavets/Estimated reading time: 6 minutes
GanttPRO Wins Prestigious Awards in Project Management, Marketing Planning, Project Tracking, and More
Paolo Kukhnavets/Estimated reading time: 7 minutes
How to Precisely Track Time Spent on Tasks with GanttPRO: the Timer Widget in the Mobile App
Andrew Stepanov/Estimated reading time: 1 minute
How to Boost Productivity with GanttPRO: Integrations with Google and Outlook Calendars
Andrew Stepanov/Estimated reading time: 4 minutes
How to Work with Task and Project Budget with GanttPRO: Manual Budget Entry & Currency
Andrew Stepanov/Estimated reading time: 3 minutes
How to Plan and Manage Project and Resource Calendars with GanttPRO: 30-Minute Intervals
Andrew Stepanov/Estimated reading time: 1 minute
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Join 1M+ project managers!

Create Gantt charts in minutes with GanttPRO and reduce time spent on managing tasks by 40%

Try for free

No credit cards required. No obligation.

0
Would love your thoughts, please comment.x
()
x